Machining parameter to set time to remove each part from the machine
This is the time in seconds to take a part from the machine.
It is applied once per part to each cycle.
For example:-
Item Rout time (seconds)
Part 1 32
Part 2 36
Part 3 27
Part 4 45
Loading time per board = 17 seconds
Time to take off each part = 8 seconds
Cycle time = 17+(32+8)+(36+8)+(27+8)+(45+8) = 189 seconds
Note:
For nested patterns the calculation of the dividing time is base on these parameters
- Loading time per board
- Time to take off each part
- Tool in/out (pattern dividing times)
- Cutting speed (pattern dividing times)
- Rapid Speed
The speed values in the machining library tooling options (e.g. Feed speed, spindle speed) are not used when calculating the pattern dividing times.
Notes
- Can also be set as a Material parameter at material level.