Time to take off each part

 

Machining parameter to set time to remove each part from the machine

 

mct1868-01.gif

 

This is the time in seconds to take a part from the machine.

 

It is applied once per part to each cycle.

 

For example:-

 

Item        Rout time (seconds)

Part 1          32

Part 2          36

Part 3          27

Part 4          45

 

Loading time per board = 17 seconds

Time to take off each part = 8 seconds

 

Cycle time = 17+(32+8)+(36+8)+(27+8)+(45+8) = 189 seconds

 

Note:

 

For nested patterns the calculation of the dividing time is base on these parameters

 

- Loading time per board

- Time to take off each part

- Tool in/out (pattern dividing times)

- Cutting speed (pattern dividing times)

- Rapid Speed

 

The speed values in the machining library tooling options (e.g. Feed speed, spindle speed) are not used when calculating the pattern dividing times.

 

Notes

 

- Can also be set as a Material parameter at material level.

 

 

See also