Edit cutting list, board list, parameters at Review runs

 

Making last minute changes to runs

 

At the Review runs screens there are options to edit the following items.

 

- Cutting list

- Board list

- Optimising, Saw, Material parameters

- Forms and labels

 

 Move to the run

 Select an edit option from the 'Function' toolbar

 

mct2216-01.png

 

- The program moves to the cutting list, board list ...

 

(These options are also available at the Edit menu)

 

The program moves to the Cutting list or Board list or Parameter as appropriate. The lists can be edited in the usual way but there are some important restrictions to be aware of.

 

Cutting list and Board list

 

At the cutting list or board list screen only the current list is available and can be edited. Minor changes can be made and on exit the run is recalculated. If there are changes that affect the optimisation (part sizes, part quantities, board sizes ...) the current set of patterns are deleted and the run is re-optimised.

 

Parameter lists

 

Typically many runs use the same set of parameters and it is rare to change the parameter list values significantly. The program prompts to create a copy of the parameter list (this avoids changing other runs). If changes are made the program creates a snapshot of the current parameter list and names it based on the run name.

 

If any changes are made they apply only to the new list and the new list is linked to the run.

 

On exit the run is re-calculated.

 

The parameter lists on the Edit menu are as follows.

 

Optimising parameters

Saw parameters

Material parameters

Saw transfer parameters

Machining centre parameters

 

Material parameters - a run with mixed materials may use several different parameter lists. If these are edited the program prompts with the lists used - they can be selected and edited in the usual way.

 

Re-optimise

 

If the changes do not affect the patterns but there may be some under production an error is reported. The program prompts to re-optimise the data.'Some parts not produced - re-optimise list?'.

 

See also